Cape Lambert Village "B"
Problem
Cape Lambert Village “B” needed treatment for 1,200 equivalent persons – 372 kL/day – against a treated effluent specification of total phosphorus below 1 mg/L and total nitrogen below 10 mg/L.
Solution
A packaged plant sized to 1,200 EP was built and fully factory-tested before shipment. Site construction ran 20 days from mobilisation to commissioning. The plant was commissioned on influent sewage and seeded from the adjacent Cape Lambert Village “A” plant, an existing WWS plant already in service.
Outcome
The process was producing compliant final effluent within seven days of commissioning.